CN is starting work on reconfiguring the Collingwood interlocking in Duluth. This is where the ore dock leads connect to the Missabe Junction line at the base of Proctor Hill. They plan to eliminate the double track here and make a single control point that includes the switch to Missabe Junction and a single switch for the west dock lead. This will basically replace five switches with two (eliminating the crossovers within the CTC plant). There will no longer be a north and south Collingwood and the signals will be taken down on the dock by the office.

Dave Schauer

Duluth, MN